New Nuclear Plant Deployment
Current State of the Industry
Federal Financial Incentives
Summary: EPAct 2005 incentives are at various stages of development: two rules issued and one notice published.
Standby Support: Rule issued, one industry request for conditional agreements to date, no contract issued.
- Final Rulemaking Issued August 2006.
- Published Standard Conditional Agreement September 2007.
- DOE released on-line instructions for requesting Conditional Agreement December 2007.
- One request for a Conditional Agreement was received in September 2008.
- One Notice of Intent to Request a Conditional Agreement was received in 2008 and a second in February 2009.
- One Notice of Intent received in 2008 has since been withdrawn.
- Expect first DOE approval for standby support contract in 2011.
Production Tax Credits: Notice issued.
- Internal Revenue Bulletin 2006-18 published May 2006.
- Modified Guidance on Tax Credit may be issued by early 2009.
Nuclear Energy Facility Loan Guarantees: Congress provided DOE with authority to issue $20.5 billion in guaranteed loans.
- DOE issued solicitations for $18.5 billion in loan guarantees for new nuclear power facilities and $2 billion for the "front end" of the nuclear fuel cycle on June 30, 2008.
- Fifteen power companies have submitted applications, requesting a total of $93 billion in loans to be guaranteed, by the Part II deadline of 12/19/08. The applications cover 10 sites with a total of 16 reactors, capable of providing 22 GW in generating capacity.
- DOE has narrowed the power facilities under consideration for loan guarantees to five applicants, with a total of nine reactors.
- Two companies submitted $4 billion in loan guarantee applications for two front-end fuel cycle facilities, and followed up with Part II applications by the 12/2/08 deadline.