Quarterly Nuclear Deployment Summary
Moving Toward Deployment
January 2012
< Back to Scorecard
Early Site Permits (ESP)
Summary: Four ESPs issued; two under review:
- The following ESPs have been issued: Exelon – Clinton (IL), 3/15/07; Entergy – Grand Gulf (MS), 4/5/07; Dominion – North Anna (VA), 11/ 27/07; Southern – Vogtle site (GA), 08/26/09.
- On March 25, 2010, Exelon submitted an ESP application for its Victoria County site. The final SER and EIS are expected to be completed by late 2013.
- PSEG submitted an ESP application for its nuclear plant site in Salem County, New Jersey, on May 26, 2010. The final SER and EIS are expected in mid to late 2014.
- NRC anticipates two further ESP applications at Blue Castle and Callaway.