Quarterly Nuclear Deployment Summary
Moving Toward Deployment
April 2011
< Back to Scorecard
Early Site Permits (ESP)
Summary: Four ESPs issued; two under review:
- The following ESPs have been issued: Exelon – Clinton (IL), 3/15/07; Entergy – Grand Gulf (MS), 4/5/07; Dominion – North Anna (VA), 11/ 27/07; Southern – Vogtle site (GA), 08/26/09.
- On March 25, 2010, Exelon submitted an ESP application for its Victoria County site. This replaces a COL withdrawn July 2009.
- PSEG submitted an ESP application for its nuclear plant site in Salem County, New Jersey, on May 26, 2010, which was docketed August 4, 2010
- NRC anticipates two further ESP applications at Blue Castle and Callaway.