Nuclear Power Deployment Scorecard
Moving Toward Deployment
January 2010
< Back to Scorecard
Supplement
Early Site Permits (ESP)
Summary: Four ESPs issued:
- The following ESPs have been issued: Exelon – Clinton (IL), 3/15/07; Entergy – Grand Gulf (MS), 4/5/07; Dominion – North Anna (VA), 11/27/07; Southern – Vogtle site (GA), 08/26/09.
- Duke notified NRC of two possible ESP applications at Oconee County (SC) and/or Davie County (NC); no dates provided.
- Exelon is preparing an ESP for its Victoria County site, for which it had originally submitted a COL.