Quarterly Nuclear Deployment Summary
Moving Toward Deployment
January 2011
< Back to Scorecard
Reactor Design Certification (DC)
Summary: Two reactor designs are certified; three new designs and one amendment are under NRC review.
- GE ABWR – Certified in 1997 (10CFR52 App A).
- Westinghouse AP1000 – Certified 2005 (10CFR52 App D). A modification to the certified design was docketed January 18, 2008; under NRC review with rulemaking currently scheduled September 2011.
- GE ESBWR – Under NRC certification review, application docketed December 2005; rulemaking scheduled for September 2011.
- AREVA US-EPR – Submitted December 12, 2007, and docketed February 25, 2008; rulemaking expected in February 2012.
- Mitsubishi Heavy Industries US-APWR – Submitted December 31, 2007, and docketed February 29, 2008; rulemaking expected 2012.