Nuclear Power Deployment Scorecard
Powering Future Decades
December 14, 2007
< Back to Scorecard
New Nuclear Plant Deployment
Current State of the Industry
Reactor Design Certification (DC)
Summary: Two designs certified; two designs are under NRC review and one DC application expected to be submitted to NRC in December 2007.
Combined Construction and Operating License Applications (COLA) Submitted:
- GE ABWR – Certified in 1997.
- Westinghouse AP1000 – Certified 2005. A modification to the certified design is currently under NRC review.
- GE ESBWR – Under NRC certification review, application docketed December 2005.
- AREVA US EPR – Application submitted December 12, 2007, not yet docketed.
- Mitsubishi Heavy Industries US APWR – Plans to submit certification application December 2007.