Quarterly Nuclear Deployment Summary
Moving Toward Deployment
July 2012
< Back to Scorecard
Reactor Design Certification (DC)
Summary: Two reactor designs that are being considered for future builds are certified and two renewal applications are under NRC review.
- AREVA US-EPR – Submitted December 12, 2007, and docketed February 25, 2008; rulemaking expected in December 2014.
- GE ESBWR – Final Design Approval in March 2011; rulemaking expected 2013.
- Mitsubishi Heavy Industries US-APWR – Submitted December 31, 2007, and docketed February 29, 2008; rulemaking expected in 2015.
- KEPCO APR-1400 – Pre-application interactions began in January 2012. Design certification application anticipated March 2013.
- GE ABWR – Certified in 1997. Toshiba and GEH have also separately submitted Design Certification renewal applications that are currently under review.
- Westinghouse AP1000 – Amended design certified on December 30, 2011.