General Information
Document and Media Library Button
Job Opportunities Button
Sitemap Button
Stay Connected Header
Sign up for email Nuclear Energy alerts.
Jump into the Students zone!
Poster City Students click here!
Educators Header
Educators Image
Blue Ribbon Commission on America’s Nuclear Future

Quarterly Nuclear Deployment Summary

Moving Toward Deployment

July 2011

Quarterly News

  • Westinghouse submitted DCD Revision 19, which should allow the NRC to continue with the final design approval of the AP1000 later this year, although no schedule has yet been announced.


  • The Nuclear Regulatory Commission completed its Final Environmental Impact Statement for the proposed South Texas Project Units 3 and 4, Comanche Peak Units 3 and 4, Virgil C. Summer Units 2 and 3, and Calvert Cliffs Unit 3 and concluded that there are no environmental impacts that would preclude issuing Combined Licenses for construction and operation of the plants


  • Toshiba and Babcock & Wilcox have agreed to extend the deadline for USEC to secure a conditional approval for a loan guarantee with the Department of Energy until mid-August.


  • TVA has received a fuel handling license for Watts Bar 2 and expects to begin loading during the summer of 2012.


  • Ur-Energy has obtained the Supplemental Environmental Impact Statement for its Lost Creek in situ Uranium recovery project. The NRC is also completing the Safety Evaluation Report, which it anticipates to release with the final license.
COL Applications Submitted
UTILITY SITE/
LOCATION
REACTOR/
NO. UNITS
COLA
DATES
REVIEW PHASE IN PROGRESS
Submitted Docketed Safety4 Environ.5
Southern Nuclear Vogtle GA AP10001 2 3/31/08 5/30/08 Ph. 6 Completed
SCE&G V.C. Summer SC AP1000 2 3/27/08 7/31/08 Ph. D Completed
STP Nuclear Operating Co. South Texas Project TX ABWR1 2 9/07 11/29/07 Ph. 2 Completed
Luminant (TXU) Comanche Peak TX US-APWR1 2 9/19/08 12/2/08 Ph. 2 Completed
UniStar (Constellation) Calvert Cliffs MD US-EPR1 1 3/08 6/3/08 Ph. 2 Completed
DTE Energy Fermi MI ESBWR 1 09/18/08 11/25/08 Ph. 2 Ph. 2
Dominion Energy North Anna VA US-APWR 1 11/27/07 1/28/08 Ph. A Ph. 2
Duke Energy William States Lee SC AP1000 2 12/13/07 2/25/08 Ph. B Ph. 2
Florida Power and Light Turkey Point FL AP1000 2 6/30/09 9/8/09 Ph. A Ph. 2
PPL (UniStar) Bell Bend PA US-EPR 1 10/10/08 12/19/08 Ph. A Ph. 2
Progress Energy Shearon Harris NC AP1000 2 2/19/08 4/17/08 Ph. B Ph. 2
Progress Energy Levy FL AP1000 2 7/30/08 10/6/08 Ph. B Ph. 3
Suspended
Entergy (NuStart) Grand Gulf MS ESBWR 1 2/08 4/17/08 Suspended Suspended
Entergy River Bend LA ESBWR 1 9/25/08 12/4/08 Suspended Suspended
AmerenUE (UniStar) Callaway MO US-EPR 1 7/24/08 12/12/08 Suspended Suspended
UniStar (Constellation) Nine Mile Point NY US-EPR 1 9/30/08 12/11/08 Suspended Suspended
TVA (NuStart) Bellefonte AL AP1000 2 10/07 1/18/08 Suspended Suspended

1    Reference COL Application (R-COL)
4    Safety Review Phases:

R-COL: Ph 1 Issue RAIs   Ph 2 SER w/ Open Items   Ph 3 ACRS Review   Ph 4 Advanced SER/ No OI   Ph 5 ACRS Review   Ph 6 Final SER
S-COL: Ph A Issue RAIs & supplemental RAIs   Ph B Advanced SER/ No OI   Ph C ACRS Review   Ph D Final SER

5    Environmental Review Phases:

Ph 1 Environmental Scoping Report   Ph 2 Draft EIS   Ph 3 Public comment   Ph 4 Final EIS


  Nuclear Power Deployment Status

Design Certification (DC) >

  • Two reactor designs that are being considered for future builds are certified; three new designs and two amendments are under NRC review.

Early Site Permit (ESP) >

  • Four ESPs issued by NRC.
  • Two ESP applications under NRC review.
  • Two ESP applications anticipated in the near future.

New Nuclear Plant Orders >

  • Nine utilities have ordered large, long-lead nuclear component forgings from three reactor vendors.
  • Four Engineering, Procurement, and Construction Contracts signed (Vogtle, V.C. Summer, STP, and Levy).

New Plant Construction, Operation, Deferral >

  • TVA resumed construction of Watts Bar 2 and re-considering completion of Bellefonte 1 & 2.
  • Site prep work progressing for two facilities.

Federal Financial Incentives >

  • Nuclear Power Loan Guarantees – DOE authorized to guarantee $20.5 billion in loans for nuclear projects; $10.33 billion has been conditionally committed.
  • Standby Support (Risk Insurance) – DOE authorized to issue insurance to six reactors to cover delays in operations attributed to NRC licensing reviews or litigation.
  • Production Tax Credits – 1.8 cents/kw tax credit for the first 6,000 MWe of deployed nuclear power.
Inspector General | DOE Directives | Small Business
The White House Link: Energy.Gov/RECOVERY usa.gov E-gov IQ FOIA Link: Privacy Program
Web Policies | No Fear Act | Site Map | Privacy | Phone Book | Employment