Nuclear Power Deployment Scorecard
Powering Future Decades
March 5, 2009
What's New
- The South Texas Project Nuclear Operating Company signed an EPC contract with Toshiba for two ABWRs on February 25, 2009. A previous contract addressed pre-construction & licensing.
- NRC authorized the reinstatement of construction permits for TVA's unfinished Bellefonte Units 1 and 2 near Scottsboro, AL on February 19.
- The South Carolina Public Service Commission (PSC) approved SCE&G's plans for two AP1000 reactors at V.C. Summer on February 11.
- NRC published final guidance February 18 on new reactor construction activities allowed under a Limited Work Authorization (LWA).
- NRC issued an updated review schedule for the ESBWR on February 18. GEH committed to prepare Rev. 6 of the DCD resolving open items; it must be submitted by Aug. 31 to avoid delays.
- In February, DOE narrowed the reactor applicants eligible for loan guarantees to five.
- On February 13, UniStar requested that the NRC delay its review of the Nine Mile Point COLA as the company will focus its resources on the Calvert Cliffs COLA.
- NRC issued the final safety evaluation report (FSER) for Southern's ESP and LWA at the Vogtle site on February 11.
- NRC gave notice of hearings for the public to intervene in the following COLAs:
- Callaway (AmerenUE)
- Comanche Peak (Luminant)
- South Texas (STPNOC)
- DOE received a notice of intent to request a conditional agreement under its Standby Support Program on February 3.
Quick Statistics
- Early Site Permits issued—3
- Permits under review—1
- COL applications submitted—17
No. reactors submitted—26
- COL applications docketed—17
No. reactors docketed—26
Docketed but deferred—4
- Total expected license applications—23
Expected number of reactors—34
- Certified reactor designs—2
- Reactor designs under review—4
- Announced plant locations—21
- Companies applying for COL—20
Number of Planned Reactors (34)
Vendor Technology Under Consideration
General Electric
- Advanced Boiling Water Reactor (ABWR) – 1,356 MWe (certified 10CFR52 App A)
- Economic Simplified Boiling Water Reactor (ESBWR) – 1,560 MWe
Westinghouse
- Advanced Passive Pressurized Water Reactor (AP1000) – Twin units 1,117 MWe each (certified 10CFR52 App D)
AREVA
- United States Evolutionary Pressurized Water Reactor (US EPR) – 1,600 MWe
Mitsubishi Heavy Industry
- United States Advanced Pressurized Water Reactor (US APWR) – 1,700 MWe
|
|
Status of License Applications (23)
Announced Nuclear Locations
- Amarillo (TX)—Amarillo Power
- Bell Bend (PA)—PPL (formerly Susquehanna)
- Bellefonte (AL)—Tennessee Valley Authority
- Elmore County (ID)—Alternate Energy Holdings
- Callaway (MO)—AmerenUE
- Calvert Cliffs (MD)—UniStar
- Clinton (IL)—Exelon
- Comanche Peak (TX)—Luminant
- Fermi (MI)—DTE Energy
- Grand Gulf (MS)—Entergy
- Shearon Harris (NC)—Progress Energy
- Levy County (FL)—Progress Energy
- Nine Mile Point (NY)—UniStar
- North Anna (VA)—Dominion Energy
- River Bend (LA)—Entergy
- South Texas Project (TX)—STP Nuclear
- V.C. Summer (SC)—SCE&G
- Turkey Point (FL)—Florida Power & Light
- Victoria County (TX)—Exelon Generation
- Vogtle (GA)—Southern Nuclear
- William States Lee III (SC)—Duke Energy
|
|
|
|
 |
| |
Nuclear Power Deployment Scorecard |
| |
 |
Early Site Permit (ESP) > |
| |
- Three site permits issued by NRC (Clinton, Grand Gulf, North Anna)
- One site permit application under NRC review (Vogtle)
- Submission of three other ESP applications expected in 2010-2012
|
 |
Combined Construction and Operating License (COL) > |
 |
License Applications Submitted to NRC
- Thirteen COLAs docketed and under review
- Three docketed COLAs suspended pending technology decision
- One docketed COLA is delayed as the power company focuses on a previously submitted COLA
- Submission of 6 additional COLs expected in 2009-2010
|
| |
 |
Status of Reference R-COLs
- All five R-COLs have been submitted and are undergoing NRC review (Bellefonte, Calvert Cliffs, Comanche Peak North Anna, South Texas Project)
|
 |
Reactor Design Certification (DC) > |
| |
- Two advanced reactor designs certified by NRC (ABWR and AP1000)
- Four reactor designs undergoing NRC review (ESBWR, US-EPR, AP1000 amend., and US-APWR
|
 |
New Nuclear Plant Orders > |
 |
Long-Lead Equipment Orders
- Nine utilities have ordered large, long-lead nuclear component forgings from three reactor vendors
- Four steel containment shells and 24 reactor coolant pumps have been ordered for AP1000 units
- Two domestic large component facilities being built
- Japan Steel Works is the only manufacturer of ultra-large forgings; worldwide-capacity limited
|
| |
 |
Engineering, Procurement, and Construction Contracts (EPC)
- Four EPC contracts initiated (Vogtle, V.C. Summer, STP, and Progress)
- Plant engineering is in progress; completion required to start construction
|
 |
New Nuclear Plant Construction, Operation, & Deferral > |
| |
- No utility has committed to constructing a new advanced reactor
- TVA resumed construction of Watts Bar 2 and construction permits for Bellefonte 1 & 2 were reinstated
|
 |
Federal Financial Incentives > |
 |
Standby Support (Risk Insurance)
- Final 10 CFR Part 950 Rule issued August 11, 2006
- One active Notice of Intent to Request a Conditional Agreement and a second notice has been withdrawn. One formal request under review by DOE.
|
| |
 |
Production Tax Credits
- Internal Revenue Bulletin 2006-18 published May 2006
- IRS considering revised guidance
|
| |
 |
Nuclear Power Loan Guarantees
- The Department is authorized, until September 30, 2009, to guarantee $18.5 billion in loans for nuclear power projects. First NRC-issued COL not expected before mid-2011, beyond current authority period—authority extension needed to keep program viable.
- Fifteen power companies have submitted Part II applications by the December 19, 2008 deadline, requesting a total of $93 billion in loans to be guaranteed. The applications cover 10 sites with a total of 16 reactors, capable of providing 22 GW in generating capacity.
- DOE has narrowed the new reactors eligible to receive loan guarantee to five applicants.
|
|
| |
Scorecard Legend |
| |
 |
Implementation proceeding according to plan and schedule |
 |
Progress being made; however, issues or uncertainties exist that could impede progress |
 |
Unlikely to realize objectives absent significant management attention |
 |
No dates or end state established |
 |
Indicates change in status or progress since last evaluation |
 |
Regulatory Demonstration completed. No further government assistance is warranted. |
|
|
|