About DOE Button Organization Button News Button Contact Us Button
Link: Energy home page
Science and Technology Button Energy Sources Button Energy Efficiency Button The Environment Button Prices and Trends Button National Security Button Safety and Health Button
Home Button
Welcome Button
Mission Button
Our Organization Button
Our Programs Button
Advisory Committee Button
News Room Button
General Information
Document and Media Library Button
Job Opportunities Button
Sitemap Button
Stay Connected Header
Sign up for email Nuclear Energy alerts.
Jump into the Students zone!
Poster City Students click here!
Educators Header
Educators Image
Blue Ribbon Commission on America’s Nuclear Future

Nuclear Power Deployment Scorecard

Powering Future Decades
March 3, 2008

What's New

  • NRC docketed Mitsubishi's US-APWR Design Certification application on February 29, 2008.
  • Entergy and NuStart submitted a COL application for an ESBWR at Grand Gulf on February 27.
  • NRC docketed Duke's COLA for two AP1000 reactors at William States Lee III Nuclear Station on February 25.
  • NRC docketed AREVA's US-EPR Design Certification application on February 25.
  • Progress Energy submitted a COL application for two AP1000 reactors at Shearon Harris on February 19.
  • On February 13, NRC canceled a planned hearing for NRG's South Texas Project COLA; this will extend the deadline for petition to intervene.
  • On January 31, a company remaining anonymous informed NRC of its intention to submit a COL application in 2010.

Quick Statistics

  • Early Site Permits issued—3
  • Permits under review—1
  • Total COL applications submitted—6
  • Certified reactor designs—2
  • Reactor designs under review—4
  • Expected license applications—22
  • Expected number of reactors—33
  • Nuclear plant locations—19
  • Companies applying for COL—19

Number of Planned Reactors (33)

Number of Planned Reactors-- AP 1000:14, ESBWR:5, USEPR:7, ABWR:2, USAPWR:2, Unspecified:3

Vendor Technology Under Consideration

General Electric
  • Advanced Boiling Water Reactor (ABWR), 1,356 MWe (certified 10CFR52 App A)
  • Economic Simplified Boiling Water Reactor (ESBWR), 1,560 MWe
Westinghouse
  • Advanced Passive Pressurized Water Reactor (AP1000), Twin units 1,117 MWe each (certified 10CFR52 App D)
AREVA
  • United States Evolutionary Pressurized Water Reactor (US EPR), 1,600 MWe
Mitsubishi Heavy Industry
  • United States Advanced Pressurized Water Reactor (US APWR), 1,700 MWe
 

Status of License Applications (22)

Status of License Applications-- Docketed:4, Under Review for Docketing:2, Expected in 2008:13, Expected in 2009:1, Expected in 2010:2

Announced Nuclear Locations

  • Bellefonte (AL)—Tennessee Valley Authority
  • Bruneau (ID)—Alternate Holding Energy
  • Callaway (MO)—AmerenUE
  • Calvert Cliffs (MD)—UniStar
  • Clinton (IL)—Exelon
  • Comanche Peak (TX)—Luminant (formerly TXU)
  • Fermi (MI)—DTE Energy
  • Grand Gulf (MS)—Entergy
  • Shearon Harris (NC)—Progress Energy
  • Levy County (FL)—Progress Energy
  • Nine Mile Point (NY)—UniStar
  • North Anna (VA)—Dominion Energy
  • River Bend (LA)—Entergy
  • South Texas (TX)—STP Nuclear
  • V.C. Summer (SC)—SCE&G
  • Susquehanna (PA)—PPL
  • Turkey Point (FL)—Florida Power & Light
  • Vogtle (GA)—Southern Nuclear
  • William States Lee III (SC)—Duke Energy
 
 

  Nuclear Power Deployment Scorecard

 
On Schedule Early Site Permit (ESP) >
 
  • Three site permits issued by NRC (Clinton, Grand Gulf, North Anna)
  • One site permit application under NRC review (Vogtle)
  • Submission of three other ESP applications expected in 2010-2012
On Schedule Combined Construction and Operating License (COL)>
On Schedule License Applications Submitted to NRC
  • Four COL applications docketed for review by NRC (STP, Bellefonte, North Anna, and Lee)
  • One partial COLA docketed–environmental portion only (Calvert Cliffs)
  • Two COL applications submitted to NRC awaiting acceptance (Grand Gulf and Harris)
  • Submission of 16 additional COLs expected in 2008-2010
  • Three applications expected in March (V.C. Summer, Vogtle, and Calvert Cliffs)
  Unspecified Licenses to Build Issued by NRC
  • NRC anticipates issuing COL 42 months after docketing
On Schedule Reactor Design Certification (DC) >
 
  • Two advanced reactor designs certified by NRC (ABWR and AP 1000)
  • Four reactor designs undergoing NRC certification review (ESBWR, US-EPR, AP1000 amendment, and US-APWR)
Delayed New Nuclear Plant Orders >
Delayed Long-Lead Equipment Orders
  • Six utilities have ordered large long-lead nuclear component forgings with three reactor vendors
  • No other long-lead equipment (e.g., heat exchanger and generator) have been ordered to date
  • Japan Steel Works is only manufacturer of ultra-large forgings worldwide–capacity limited
  Delayed Engineering, Procurement and Construction Contracts (EPC)
  • No plant contracts signed to date; negotiations on-going among vendors and several utilities
  • Plant engineering in progress; completion required to start construction
Unspecified New Nuclear Plant Construction, Operation & Deferral >
 
  • No utility has committed to constructing a new plant
Delayed Federal Financial Incentives >
On Schedule Standby Support (Risk Insurance)
  • Final 10 CFR Part 950 Rule issued August 11, 2006
  • Standard Conditional Agreement issued September 2007
  • DOE released on-line instructions to request a Conditional Agreement in December 2007
  On Schedule Production Tax Credits
  • Internal Revenue Bulletin 2006-18 published May 2006
  • Publish regulation for Production Tax Credit in FY08
  Delayed Energy Facility Loan Guarantee
  • Final 10 CFR Part 609 Rule amended January 18, 2008
  • Solicitation for small scale loan guarantees closed December 2006
  • No solicitation issued for nuclear plant loan guarantees
  • $18.5 billion approved for loan guarantees for nuclear plants December 2007


 
  Scorecard Legend
 
On Schedule Implementation proceeding according to plan and schedule
Delayed Progress being made; however, issues or uncertainties exist that could impede progress
Failure Unlikely to realize objectives absent significant management attention
Unspecified No dates or end state established
Arrows Indicates change in status or progress since last evaluation
Check Regulatory Demonstration completed. No further government assistance is warranted.

folder iconArchived Scorecards
printer icon Scorecard - Printer Friendly Version (PDF 512 KB)
(Prints best on legal size paper - 8½ x 14)
Inspector General | DOE Directives | Small Business
The White House Link: Energy.Gov/RECOVERY usa.gov E-gov IQ FOIA Link: Privacy Program
Web Policies | No Fear Act | Site Map | Privacy | Phone Book | Employment