Nuclear Power Deployment Scorecard
Powering Future Decades
February 8, 2008>
What's New
- On February 8, 2008, NRC noticed a future hearing to allow the public an opportunity to intervene in the Bellefonte COLA.
- The U.S. Air Force is holding an Energy Forum on March 3, 2008 to explore hosting a nuclear plant at a USAF installation (http://usafenergyforum.com).
- On February 4th, NRC announced a public meeting for the Grand Gulf COL to be held on Feb. 21, 2008.
- NRC docketed the environmental portion of UniStar's COLA for Calvert Cliffs Jan. 31st.
- Transition Power Development notified the NRC January 30th that it intends to submit a COL and/or ESP for the Blue Castle Generation Project in Utah by April 2010.
- NRC docketed the Dominion COL application for review on January 25th.
- NRC docketed an amendment to the Westinghouse AP1000 Design Certification on January 18th.
- The Loan Guarantee Rule was revised January 18th to correct publication errors.
- MidAmerican ended its pursuit of a COL for a plant in Idaho on January 15th.
- See most recent Scorecard updates at http://www.nuclear.gov/.
Quick Statistics
- Early Site Permits issued—3
- Permits under review—1
- Total COL applications submitted—4
- Certified reactor designs—2
- Reactor designs under review—4
- Expected license applications—20
- Expected number of reactors—31
- Nuclear plant locations—19
- Companies applying for COL—17
Number of Planned Reactors (31)
Vendor Technology Under Consideration
General Electric
- Advanced Boiling Water Reactor (ABWR), 1,356 MWe (certified 10CFR52 App A)
- Economic Simplified Boiling Water Reactor (ESBWR), 1,540 MWe
Westinghouse
- Advanced Passive Pressurized Water Reactor (AP1000), Twin units 1,117 MWe each (certified 10CFR52 App D)
AREVA
- United States Evolutionary Pressurized Water Reactor (US EPR), 1,600 MWe
Mitsubishi Heavy Industry
- United States Advanced Pressurized Water Reactor (US APWR), 1,700 MWe
Status of License Applications (20)
Announced Nuclear Locations
- Bellefonte (AL)—Tennessee Valley Authority
- Bruneau (ID)—Alternate Holding Energy
- Callaway (MO)—AmerenUE
- Calvert Cliffs (MD)—UniStar
- Clinton (IL)—Exelon
- Comanche Peak (TX)—Luminant (formerly TXU)
- Fermi (MI)—DTE Energy
- Grand Gulf (MS)—Entergy
- Harris (NC)—Progress Energy
- Levy County (FL)—Progress Energy
- Nine Mile Point (NY)—UniStar
- North Anna (VA)—Dominion Energy
- River Bend (LA)—Entergy
- South Texas (TX)—STP Nuclear
- Summer (SC)—SCE&G
- Susquehanna (PA)—PPL
- Turkey Point (FL)—Florida Power & Light
- Vogtle (GA)—Southern Nuclear
- William Lee (SC)—Duke Energy
| |
Nuclear Power Deployment Scorecard |
| |
 |
Early Site Permit (ESP) |
| |
- Three site permits issued by NRC (Clinton, Grand Gulf, North Anna)
- One site permit application under NRC review (Vogtle)
- Submission of three other ESP applications expected in 2010-2012
|
 |
Combined Construction and Operating License (COL) |
 |
License Applications Submitted to NRC
- Three COL applications docketed for review by NRC (STP, Bellefonte, and North Anna)
- One partial COLA docketed–environmental portion only (Calvert Cliffs)
- One COL application submitted to NRC (William Lee)
- Submission of 16 additional COLs expected in 2008-2009
|
| |
 |
Licenses to Build Issued by NRC
- NRC anticipates issuing COL 42 months after docketing
|
 |
Reactor Design Certification (DC) |
| |
- Two advanced reactor designs certified by NRC (ABWR and AP 1000)
- Two reactor designs undergoing NRC certification review (ESBWR and AP1000 amendment)
- Two DC applications submitted to NRC, but not yet docketed (US-APWR and US-EPR)
|
 |
New Nuclear Plant Orders |
 |
Long-Lead Equipment Orders
- Six utilities have ordered large long-lead nuclear component forgings with three reactor vendors
- No other long-lead equipment (e.g., heat exchanger and generator) have been ordered to date
- Japan Steel Works is only manufacturer of ultra-large forgings worldwide–capacity limited
|
| |
 |
Engineering, Procurement and Construction Contracts (EPC)
- No plant contracts signed to date; negotiations on-going among vendors and several utilities
- Plant engineering in progress; completion required to start construction
|
 |
New Nuclear Plant Construction, Operation & Deferral |
| |
- No utility has committed to constructing a new plant
|
 |
Federal Financial Incentives |
 |
Standby Support (Risk Insurance)
- Final 10 CFR Part 950 Rule issued August 11, 2006
- Standard Conditional Agreement issued September 2007
- DOE released on-line instructions to request a Conditional Agreement in December 2007
|
| |
 |
Production Tax Credits
- Internal Revenue Bulletin 2006-18 published May 2006
- Publish regulation for Production Tax Credit in FY08
|
| |
 |
Energy Facility Loan Guarantee
- Final 10 CFR Part 609 Rule amended January 18, 2008
- Solicitation for small scale loan guarantees closed December 2006
- No solicitation issued for nuclear plant loan guarantees
- $18.5 billion approved for loan guarantees for nuclear plants December 2007
|
|
| |
| Scorecard Legend |
| |
 |
Implementation proceeding according to plan and schedule |
 |
Progress being made; however, issues or uncertainties exist that could impede progress |
 |
Unlikely to realize objectives absent significant management attention |
 |
No dates or end state established |
 |
Indicates change in status or progress since last evaluation |
 |
Regulatory Demonstration completed. No further government assistance is warranted. |
|
|
|
 |
|